If you have any questions, please contact the Engineering Department at 763-706-3700.  Thank you for your patience and cooperation.

2016 Water Tower Rehabilitation
The City of Columbia Heights has one 250,000 gallon water tower located at 4650 Stinson Boulevard. The last major renovation to the water tower was done in 1996.

The City of Columbia Heights will be conducting major maintenance on the water tower that involves removing the paint on the exterior and interior of the steel water tank, making repairs to the steel, and installing a new coating system on both the interior and exterior of the tank. 

It is anticipated that work on the tank will begin April 18 and continue for approximately 8-10 weeks. However, the painting/coating system is very weather dependent on both temperature and humidity, so this schedule is subject to change.

Stinson Boulevard Reconstruction

The complete reconstruction of Stinson Boulevard from 37th Avenue to Silver Lane is scheduled to begin April 4, 2016.  The work will include replacing the concrete surface with a new bituminous surface, new water main, new storm sewer, an 8-foot wide trail, and new street lighting.  In addition, CenterPoint Energy will begin replacing existing gas main along the east side of Stinson Boulevard. 

 

Unfortunately, construction activities will generate dust, noise, and temporary inconveniences. Construction may also generate vibrations from time-to-time. It is our goal to minimize the impact to residents and businesses during construction activities.

Metro Transit Route 801 will be detoured during the construction period. 

We thank you for your patience in dealing with these construction issues.

Stinson Boulevard Update October 6, 2016
Stinson Boulevard Update September 23, 2016
Stinson Boulevard Update August 18, 2016
Stinson Boulevard Update August 12, 2016
Stinson Boulevard Update July 25, 2016
Stinson Boulevard Update July 15, 2016
Stinson Boulevard Update June 30, 2016
Stinson Boulevard Update June 10, 2016
Stinson Boulevard Update May 27, 2016
Stinson Boulevard Update May 20, 2016

Stinson Boulevard Update May 13, 2016
Stinson Boulevard Update May 6, 2016
Stinson Boulevard Update April 29, 2016
Stinson Boulevard Upate April 22, 2016
Stinson Boulevard closure information


2016 Full Street Reconstruction
¤ Stinson Boulevard: 37th to 150 feet north of 40th Avenue
¤ Joint project with City of St. Anthony

2016 STREET CONSTRUCTION PROJECTS MAP

2016 Seal Coat
2nd Street: 40th Avenue to 43rd Avenue             39th Avenue: Main Street to 2nd Street
2nd Street: 44th Avenue to 45th Avenue             41st Avenue: Main Street to 3rd Street
2½ Street: 44th Avenue to 45th Avenue              42nd Avenue: Main Street to 2nd Street
3rd Street: 40th Avenue to 42nd Avenue             43rd Avenue: Main Street to 2nd Street
3rd Street: 44th Avenue to 45th Avenue

2016 Mill & Overlay
Contractor's Schedule:  May change depending on weather and other factors.
41st Avenue: Reservoir Boulevard to Stinson Boulevard
Jefferson Street:  40th Avenue to 44th Avenue

August 22, 2016 Update:
Concrete curb and gutter, pedestrian ramps and sidewalk are scheduled for the weeks of August 22nd and 29th.  Street patching and restoration will follow.

Shortly after Labor Day the pavement surface will be milled and the streets paved.

2016 Partial Street Reconstruction and/or Full Depth Reclamation (FDR)
Contractor's Schedule:  May change depending on weather and other factors.
  43rd Avenue: Reservoir Boulevard to Arthur Street
*45th Avenue: Main Street to dead end at University Avenue
    *Joint project with City of Fridley

August 22, 2016 Update 43rd Avenue: The final lift of bituminous will be paved when 41st Avenue is paved.

August 22, 2016 Update 45th Avenue:  The final lift of bituminous is tentatively scheduled for paving in early September.

2016 Water Main Cleaning and Lining

This summer, the City of Columbia Heights, working cooperatively with the Minneapolis Water Works, will clean and line approximately 4,874 lineal feet of water main. The 2016 program area includes:

  • Arthur Street from 40th Avenue to 43rd Avenue
  • 40th Avenue from Central Avenue to Reservoir Boulevard
  • 40th Avenue from Hayes Street to Arthur Street
  • Cleveland Street from 40th Avenue to 41st Avenue

September 6, 2016 Update:  The 2016 program area is progressing slower than anticipated due to unexpected delays.  Public Works crews experienced unmarked gas services that have slowed the completion of the excavations to access the water main. Rain events have also impacted the schedule as the excavations have to be pumped and dried. We appreciate your patience throughout these delays.

The water main cleaning and lining contractor completed cleaning the water main in the program area on Monday, August 29.  The City of Minneapolis will work in conjunction with the contractor to reassemble the water main, disinfect the lined main and put it back in service as soon as possible.  The City of Columbia Heights will follow up with filling and compacting the excavations and street repairs.  The water main cleaning and lining project is currently approximately 65% complete.  The work is scheduled for completion in 4-5 weeks, weather permitting.


.